Chennai Metro Rail underground station work is fast
progressing along Anna Nagar Second Avenue near Blue Star junction According to
official Chennai Metro Rail sources, about 50 per cent of track laying work of
Chennai Metro Rail Limited (CMRL) has been completed on the elevated stretch of
corridor II between Koyambedu and St. Thomas Mount.
The elevated stretch has
eight stations. The track along this stretch will be over 10 km in length and
so far, parallel train tracks have been laid for a distance of 4.3 km. It is
reported that deadline for the elevated stretch is the first quarter of 2014.