Speedy Progress Of Metro Rail Underground Work

Chennai Metro Rail tunnel work is going on in full speed. A tunnel boring machine that was launched from Nehru Park towards Egmore and 50m of tunneling work has been completed. Diaphragm wall construction has been fully completed in Washermenpet, May Day Park, Nehru Park & Shenoy Nagar. Casting of precast tunnel segments for all packages is in progress at casting yards. 

About 65 diaphragm wall panels and 12 plunge columns is completed at KMC and about  63 diaphragm wall panels is also completed at Pachaiyappas College station. 

According to official Metro Rail sources, 52 diaphragm wall panels is completed at Anna Nagar Tower station and  54 Diaphragm wall panels is completed at Thirumangalam station.