Dr. Sudhir Krishna, IAS., Chairman,
CMRL / Secretary to Government of India, Ministry of Urban Development.
inspected the underground works at Nehru Park Station on17/04/12.
During the
inspection, MD Thiru K. Rajaraman, IAS, Directors Tmt. SudhaKrishnan, IAS.,
Thiru Sathish Kumar and senior officials of CMRL were also present.
The last
section of preliminary work required to start the dredging of the metro tunnels
has touched the finishing stage.
According to senior officials of Chennai Metro
Rail Limited, the base-slab construction work at Nehru Park station,
Poonamallee High Road, where the first tunnelling is expected to start is
almost over. After the base-slab construction, finishing touches would be given
before starting the tunnel boring machines.
According to Chennai Metro Rail
sources, TBM shafts at Nehru Park, May Day Park, Shenoy Nagar are nearing
completion. Trained manpower would be resourced from China. Moreover the
excavation of launching shafts for TMBs has been completed at Nehru Park.